July 21, 2000 6:30am - Tim Elswick (Contractor) arrives to survey the job. His helper shows up shortly after. Jay and I help to remove the awning and deck. The lumber arrives from 84 Lumber and Teays Valley Heating and Cooling arrives to move the air unit. The Terramite broke down and the guys had to go get another one, which cost an hour or so on time. We had to take down the big tree in the back yard because it was too close to the foundation line. More troops arrived to make up lost time. But, an old septic tank was found right in the way of the footer, which was full. So, we had to call someone to pump it out. So, the guys left around 5:45 since the septic tank people could not come until 7:30. This page was created with ArcSoft PhotoBase. |